Kaheawa Wind I extension - 30 MW wind repowering, Ukumehame, Maui - Stage 3 RFP
Repowering/extension of Maui's first wind farm. Selected Dec 2023 in Stage 3 Maui final award. Not solar - included for completeness of Stage 3 awards. RFP: Stage 3 Maui final award (Dec 2023). Hawaii PUC docket: Stage 3 Maui. Expected/actual COD: Expected 2026. Contract term: 25 years.
Deal Value
30MW
Capacity
Wind
Technology
HI
Location
Deal Details
- Deal Type
- Utility PPA
- Seller / Sponsor
- TerraForm Power / Kaheawa Wind I LLC
- Buyer / Financier
- HECO (MECO)
- Offtaker
- HECO (MECO)
- Stage
- Operating
- ISO/RTO
- HI
- Source
- Maui News
Related Deals
Kahana Solar + Storage - 20 MW solar + 20 MW / 80 MWh BESS (4hr), West Maui - Stage 2 RFP
Innergex Renewable Energy → HECO (MECO)
Barbers Point Solar + Storage (Kalaeloa Solar Energy) - 15 MW solar + 15 MW / 60 MWh BESS (4hr), Kalaeloa, Oahu - Stage 2 RFP
Innergex Renewable Energy → HECO (MECO)
Pulehu Solar + Storage - 40 MW solar + 40 MW / 160 MWh BESS (4hr) [later revised to 20 MW / 80 MWh], Pulehu, Maui - Stage 2 RFP / Stage 3 reaward
Longroad Energy → HECO (MECO)
Amazon Wind Farm Texas / Dermott Wind — 253 MW onshore wind, Scurry County, Texas (ERCOT). Original PPA signed Sept 2015 with Lincoln Clean Energy; LCE acquired by Ørsted Aug 2018. Project COD October 19, 2017.
Lincoln Clean Energy (acquired by Ørsted Aug 2018) → Amazon
Summit Farms Solar — 60 MW solar, Currituck County, North Carolina (Duke)
Dominion Energy → MIT (consortium with Boston Medical Center + Post Office Square Redev)
SCDA Solar 1 (Sacramento Airport PV) has North and East site — Solar project, CA (CAISO), 6.800000000000001 MW, COD 2017.