Pulehu Solar + Storage - 40 MW solar + 40 MW / 160 MWh BESS (4hr) [later revised to 20 MW / 80 MWh], Pulehu, Maui - Stage 2 RFP / Stage 3 reaward
Originally 40 MWac/160 MWh in 2020 Stage 2 award; postponed 2022 due to global supply-chain crisis; reselected in Stage 3 Maui final award (Dec 2023) at reduced 20 MWac/80 MWh size to fit Maui grid constraints. Pair to Mahi Solar (Oahu). RFP: Stage 2 then Stage 3 (re-selected after 2022 supply-chain postponement). Hawaii PUC docket: Stage 3 Maui. Expected/actual COD: Expected 2027-2028. Contract term: 25 years. Storage component: 20 MW / 80 MWh (4h duration).
Deal Value
20MW
Capacity
80MWh
Storage
Solar + Storage
Technology
HI
Location
Deal Details
- Deal Type
- Utility PPA
- Seller / Sponsor
- Longroad Energy
- Buyer / Financier
- HECO (MECO)
- Offtaker
- HECO (MECO)
- Stage
- Operating
- ISO/RTO
- HI
Related Deals
Prospero Solar — 379 MW solar, Andrews County, Texas (ERCOT)
Longroad Energy / Shell → Meta (Facebook)
Knox County Wind — 123 MW wind, TX (ERCOT)
Longroad Energy → Crown Holdings
Serrano — 220 MWdc solar + 214 MWac / 855 MWh storage, Pinal and Pima Counties, Arizona
Longroad Energy → CIBC (lead), Societe Generale
220 MW
AES Hawaii portfolio — 5 solar+storage projects (224.5 MW gen / 685 MWh storage): Waikoloa, West Oahu, Mountain View, Ke'amuku
AES Corporation → Bank syndicate
$488M non-recourse
Mililani I Solar + Storage - 39 MW solar + 39 MW / 156 MWh BESS (4hr), Mililani, Oahu - Stage 1 RFP
Clearway Energy Group → HECO
Amazon Wind Farm Texas / Dermott Wind — 253 MW onshore wind, Scurry County, Texas (ERCOT). Original PPA signed Sept 2015 with Lincoln Clean Energy; LCE acquired by Ørsted Aug 2018. Project COD October 19, 2017.
Lincoln Clean Energy (acquired by Ørsted Aug 2018) → Amazon