Honeysuckle Solar — 188 MW (Google share) of 188 MW project, St. Joseph County, Indiana (MISO)
188 MW. 10 miles west of South Bend, IN. Powers Google's $2B Fort Wayne data center campus. COD October 2024. Companion event to fin-2024-028 (project financing 368 MW portfolio with AEP/McDonald's as offtakers). FERC EQR shows Google as the actual customer for Honeysuckle leg. Discovered via FERC EQR cross-reference.
Deal Value
188MW
Capacity
Solar
Technology
IN
Location
Deal Details
- Deal Type
- Power Purchase & Offtake
- Seller / Sponsor
- Lightsource bp
- Buyer / Financier
- Offtaker
- Stage
- Operating
- ISO/RTO
- MISO
- Source
- Lightsource bp
Related Deals
Lupinus + Lupinus 2 Solar — ~400 MWac combined (520 MWdc), Franklin County, Texas (Hagansport)
Sunraycer Renewables (Crayhill Capital Management) → Google Energy LLC
Undisclosed (long-term)
Project Cannoli — 1,600 MW solar + 480 MW battery storage + demand flexibility resources supporting a 1 GW data center campus, Van Buren Township, Michigan
DTE Energy → Google (Alphabet Inc.)
Undisclosed (20-year term; assets built at Google's cost)
Intersect Power platform — digital power / data center + clean energy infrastructure (10.8 GW portfolio at close)
Greenbelt Capital Partners; TPG Rise Climate; Climate Adaptive Infrastructure (CAI) → Alphabet (Google)
$12B enterprise value ($4.75B cash + assumed debt)
Wheatland Solar — 210 MWdc / 150 MWac utility-scale solar, Knox County, Indiana
Origis Energy → J.P. Morgan; MUFG
Mammoth Solar (Mammoth South + Mammoth Central I + Mammoth Central II) — 900 MWac (3× 300 MWac) of 1.3 GW Mammoth Solar complex, Pulaski County, Indiana (MISO)
Doral Renewables → KeyBanc Capital Markets, Santander, HSBC (debt); Truist (tax equity)
$1.5B
Buckleberry Solar — Solar project, NC (CPLE). MW not publicly disclosed.
Buckleberry Solar, LLC → Duke Energy Progress, LLC