NewQ1 2026 Clean Energy Deal Intelligence Report is live
PPAAnnouncedPress / newsMarch 16, 2026

Project Cannoli — 1,600 MW solar + 480 MW battery storage + demand flexibility resources supporting a 1 GW data center campus, Van Buren Township, Michigan

DTE Energy Board approved a Primary Supply Agreement (PSA) and Clean Capacity Accelerator Agreement (CCAA) with Google for a 1 GW data center campus ("Project Cannoli") in Van Buren Township, MI. Under the CCAA, DTE Electric will deploy up to 1,600 MW of renewable generation and 480 MW of energy storage at Google's cost over a 20-year term. Total new resources: 2,700 MW (including demand flexibility). Service begins December 2027, reaching full load in late 2028. Requires Michigan PSC (MPSC) regulatory approval. Disclosed via DTE Energy 8-K SEC filing March 16, 2026.

Undisclosed (20-year term; assets built at Google's cost)

Deal Value

1,600MW

Capacity

Solar

Technology

MI

Location

Project: Project CannoliAsset profile →

Deal Details

Deal Type
Power Purchase & Offtake
Seller / Sponsor
DTE Energy
Buyer / Financier
Google (Alphabet)
Offtaker
Google (Alphabet)
Deal Value
Undisclosed (20-year term; assets built at Google's cost)
Stage
Development
ISO/RTO
MISO

Related Deals

Get deals like this in your inbox

Free weekly clean energy deal intelligence. Every Monday.

← Back to Deal Database