PPAClosedJanuary 1, 2020

Mountain View Solar + Storage - 7 MW solar + 7 MW / 28 MWh BESS (4hr), Mountain View, Hawaii Island - Stage 2 RFP

Smaller community-sited project in Mountain View, Hawaii Island. 25-year PPA at $0.13/kWh. Construction began Aug 2023. Powers ~5,000 homes. Project size was reduced and redesigned after community input. RFP: Stage 2 Hawaii Island RFP. Hawaii PUC docket: Stage 2 Hawaii. Expected/actual COD: Expected 2025-2026. Contract term: 25 years. Storage component: 7 MW / 28 MWh (4h duration).

Deal Value

7MW

Capacity

28MWh

Storage

Solar + Storage

Technology

HI

Location

Deal Details

Deal Type
Utility PPA
Seller / Sponsor
AES Distributed Energy
Buyer / Financier
HECO (HELCO)
Offtaker
HECO (HELCO)
Stage
Operating
ISO/RTO
HI