NewQ1 2026 Clean Energy Deal Intelligence Report is live
PPAClosedOctober 9, 2018

Mililani I Solar + Storage - 39 MW solar + 39 MW / 156 MWh BESS (4hr), Mililani, Oahu - Stage 1 RFP

Oahu's first utility-scale solar+storage plant. $140M construction cost. PPA at $0.09/kWh. Selected as part of HECO's 7-project Stage 1 RFP batch (Oct 2018), approved by PUC March 2019. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0430. Expected/actual COD: 2022-08-11. Contract term: 25 years. Storage component: 39 MW / 156 MWh (4h duration).

Deal Value

39MW

Capacity

156MWh

Storage

Solar + Storage

Technology

HI

Location

Deal Details

Deal Type
Utility PPA
Seller / Sponsor
Clearway Energy Group
Buyer / Financier
HECO
Offtaker
HECO
Stage
Operating
ISO/RTO
HI

Related Deals

Get deals like this in your inbox

Free weekly clean energy deal intelligence. Every Monday.

← Back to Deal Database