Hermes 2 advanced nuclear reactor — 50 MW at Oak Ridge, Tennessee
First time a US utility (TVA) has entered a PPA to buy power from a Gen IV reactor. 50 MW output to TVA grid powering Google data centers in TN and AL. Kairos increased output from 28 MWe to 50 MWe.
50MW
Capacity
Other
Technology
TN
Location
Deal Details
- Deal Type
- Corporate PPA
- Seller / Sponsor
- Kairos Power
- Buyer / Financier
- Google (via TVA)
- Offtaker
- Google (via TVA)
- Deal Value
- Undisclosed
- Stage
- Development (COD 2030)
- ISO/RTO
- TVA
- Tenor
- Long-term
- Source
- Kairos Power
Related Deals
Fleet of advanced nuclear SMR reactors — 500 MW total capacity by 2035
Kairos Power → Google
500 MW
80 MW PPA from the 471 MW Mockingbird Solar Center under construction near Paris, Texas — brings project to fully contracted status
Orsted (Mockingbird Solar Center) → Bloomberg LP
Juniper IIA Wind Farm — 98.4 MW onshore wind, Oregon
Iberdrola / Avangrid → Amazon
98 MW
Timber Road IV Wind Farm — 125 MW in Paulding County, Ohio
EDP Renewables North America → Microsoft
125 MW
Wilkinson Solar Energy Center — 74 MW solar in North Carolina
Invenergy → Microsoft
74 MW
162 MWac solar offtake from 180 MWac solar project, Texas
EDP Renewables North America → Walmart
162 MW