Thunderhead Wind Energy Center, 300 MW (COD 2020).
AT&T 300 MW VPPA with Invenergy's Thunderhead Wind Energy Center in Antelope/Wheeler Counties, Nebraska. Announced Nov 5 2019. PPA price not disclosed publicly; will be imputed from regional comparables. Discovered via DealFlow research sweep (agent: 2019-backfill).
Deal Value
300MW
Capacity
Wind
Technology
NE
Location
Deal Details
- Deal Type
- Corporate VPPA
- Seller / Sponsor
- Invenergy
- Buyer / Financier
- AT&T
- Offtaker
- AT&T
- Stage
- Operating
- ISO/RTO
- SPP
- Source
- Renewables Now
Related Deals
Bethel Wind Energy Center — ~250 MW onshore wind, Castro County, Texas (ERCOT)
Southern Power / Invenergy → Google
Wind Catcher — 2,000 MW OK Panhandle (800 GE 2.5 MW turbines) + 350-mile 765kV line ($4.5B; cancelled July 2018)
AEP / Public Service of OK + SWEPCO + Invenergy → PSO + SWEPCO ratepayers
$4.5B (announced; cancelled)
Santa Rita Wind Energy Center — 125 MW wind, TX (ERCOT)
Invenergy → Kimberly-Clark
Rattlesnake Creek Wind — 320 MW wind, NE (SPP)
Enel Green Power → Adobe/Facebook (Meta)
Haystack Wind (PepsiCo share) — 100 MW wind, NE (SPP)
Ørsted → PepsiCo
Amazon Wind Farm Texas / Dermott Wind — 253 MW onshore wind, Scurry County, Texas (ERCOT). Original PPA signed Sept 2015 with Lincoln Clean Energy; LCE acquired by Ørsted Aug 2018. Project COD October 19, 2017.
Lincoln Clean Energy (acquired by Ørsted Aug 2018) → Amazon
Get deals like this in your inbox
Free weekly clean energy deal intelligence. Every Monday.