Plant Vogtle Unit 3 — 1,117 MW Westinghouse AP1000 PWR (first new US nuclear in 30+ years)

Vogtle Unit 3 fuel load — first new US nuclear fuel load in 30+ years. NRC granted 103(g) finding allowing fuel load Aug 2022; 157 fuel assemblies loaded into reactor core Oct 14, 2022. Unit went commercial Q3 2023. Total Vogtle 3+4 cost ~$30B+.

$30.00B

Deal Value

1,117MW

Capacity

Nuclear

Technology

GA

Location

Deal Details

Deal Type
Project Finance
Seller / Sponsor
Georgia Power (45.7%) + Oglethorpe Power + MEAG Power + Dalton Utilities; Southern Nuclear (operator); Westinghouse + Bechtel (construction)
Deal Value
~$30B+ total Vogtle 3+4 cost
Stage
Construction
ISO/RTO
SERC

Related Deals

FinancingMay 2026

Solar Landscape distributed/community solar warehouse facility — anchors 146 MW community solar portfolio across New Jersey, Illinois, Maryland, and Minnesota

Solar Landscape → First Citizens Bank

$600M

FinancingMay 2026

Moment Energy Series B — capitalizes North American second-life EV battery storage factory (the company has stated it will be the world's largest second-life battery factory)

Moment Energy → Evok Innovations (lead); Liberty Mutual Investments; W23 Global; Acario (Tokyo Gas CVC); existing investors: Amazon Climate Pledge Fund, Voyager Ventures, In-Q-Tel

$40M

FinancingMay 2026

CTECS 7-school solar portfolio — 4.7 MW total across 7 Connecticut technical high schools (Cheney 757 kW, Kaynor 449 kW, Prince 171 kW, Eli Whitney 833 kW, Emmett O'Brien 898 kW, Henry Abbott 657 kW, H.H. Ellis 959 kW); rooftop + carport behind-the-meter solar serving the state trade-school system

Verogy → Connecticut Green Bank

$5.4M projected lifetime energy savings to CTECS

FinancingMay 2026

Iron Spur Solar — 140 MWdc utility-scale solar PV, Snyder, Scurry County, Texas (ERCOT); ~317 GWh/yr expected production

Energea (CT Solar One, LLC SPV) → Energea (Solar in the USA Portfolio — secured convertible loan)

$5M (initial $762K advanced)

FinancingApr 2026

Cottage Grove BESS — 80 MW / 320 MWh standalone battery energy storage co-located with the 265 MW Cottage Grove cogen plant in MISO Zone 1, Minnesota

PanCentral / CGC Holdings → QIC

$33M

FinancingApr 2026

Sunrun 2026-1 — $584M residential solar + storage ABS backed by 38,706 customer leases & PPAs across 19 states + DC + Puerto Rico; A-1 notes priced at 220 bps spread (20 bps tighter than 2025 transactions)

Sunrun Inc. → Atlas SP (sole structuring agent + joint bookrunner); BofA Securities, MUFG, Truist Securities (joint bookrunners); ING (co-manager)

$584M

Get deals like this in your inbox

Free weekly clean energy deal intelligence. Every Monday.

← Back to Deal Database