DateDeal TypeTechSeller / SponsorBuyer / FinancierSizeLocationStatusNotes
Oct 9Utility PPASolar+BESSClearway Energy GroupHECO39 MWHIClosedOahu's first utility-scale solar+storage plant. $140M construction cost. PPA at $0.09/kWh. Selected as part of HECO's 7-project Stage 1 RFP batch (Oct 2018), approved by PUC March 2019. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0430. Expected/actual COD: 2022-08-11. Contract term: 25 years. Storage component: 39 MW / 156 MWh (4h duration).
Oct 9Utility PPASolar+BESSClearway Energy GroupHECO36 MWHIClosedOahu's second utility-scale solar+storage. On 40-year lease from Kamehameha Schools in Central Oahu. Includes $200K+ workforce/community benefit package with Kamehameha Schools and Blue Planet Foundation. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0433. Expected/actual COD: 2023-01. Contract term: 25 years. Storage component: 36 MW / 144 MWh (4h duration).
Oct 9Utility PPASolar+BESSAES Distributed Energy (AES Hawaii)HECO12.5 MWHIClosedAES Hawaii's first solar+storage project in Hawaii. 25-year PPA at $0.115/kWh. 80 acres near University of Hawaii-West Oahu. Delayed from initial 2021 COD to April 2024 commissioning. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0432. Expected/actual COD: 2024-04. Contract term: 25 years. Storage component: 12.5 MW / 50 MWh (4h duration).
Oct 9Utility PPASolar+BESSInnergex Renewable EnergyHECO (Hawaiian Electric Light Co / HELCO)30 MWHIClosedLocated on historic Parker Ranch land near Waimea. Innergex closed $100M loan to finance the project. 25-year PPA with HELCO. COD March 25, 2025. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0435. Expected/actual COD: 2025-03-25. Contract term: 25 years. Storage component: 30 MW / 120 MWh (4h duration).
Oct 9Utility PPASolar+BESSAES Distributed Energy (AES Hawaii)HECO (HELCO)30 MWHIClosedLargest renewable project on Hawaii Island at COD. 25-year PPA at $0.09/kWh. 30 MWac/43 MWdc bifacial single-axis trackers + 30 MW/120 MWh BESS. Increased Hawaii Island RPS from 48% to 54%. Powers ~13,600 homes. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0436. Expected/actual COD: 2023-04. Contract term: 25 years. Storage component: 30 MW / 120 MWh (4h duration).
Oct 9Utility PPASolar+BESSAES Distributed Energy (AES Hawaii)HECO (MECO - Maui Electric)60 MWHIClosedHawaii's largest solar facility (at COD). 25-year PPA at $0.08/kWh - one of the lowest in the state for renewable energy. 450 acres leased from Mahi Pono in Central Maui. Operational May 31, 2024. RFP: Stage 1 (2018 RFP). Hawaii PUC docket: Docket 2018-0434. Expected/actual COD: 2024-05-31. Contract term: 25 years. Storage component: 60 MW / 240 MWh (4h duration).
Oct 8Corporate M&ASolar+BESSApollo Global Management funds$1.00BMulti-stateClosedApollo acquires ~20 equity investments from GE Capital EFS for ~$1B. Major GE divestiture as part of broader retrenchment.

Change of Control

8 moves

Michael A. Brown joined as Senior Vice President, General Counsel and Corporate Secretary at Clearway Energy, Inc. (from Vice President, Assistant General Counsel and Corporate Secretary, The New York Times Company)

Clearway Energy — one of the largest US clean-energy generation owners, with assets across 27 states — brought back a former in-house lawyer to take its top legal seat, succeeding retiring GC Kevin Malcarney. Brown returns from The New York Times Company, where he was assistant GC, after an earlier 2014-2021 stint at Clearway and NRG Yield.

SEC filing

May 15

Kevin P. Malcarney departed Clearway Energy, Inc. as EVP, General Counsel and Corporate Secretary

Kevin Malcarney is retiring as Clearway Energy's top lawyer effective June 1, capping a tenure that spanned the company's growth into one of the largest US clean-energy owner-operators since he took the GC seat in 2018. He remains a non-executive employee through June 26; Michael A. Brown succeeds him.

SEC filing

May 15

Erik Johnson departed SOLV Energy as Chief Strategy Officer

Erik Johnson resigned as Chief Strategy Officer of SOLV Energy — the utility-scale solar EPC that went public in February 2026 — and transitioned to a non-executive employee role through year-end. No successor was disclosed in the 8-K.

SEC filing

May 12

Jing Nealis joined as Chief Financial Officer at NeoVolta Inc. (from Chief Financial Officer, SES AI Corporation)

NeoVolta, a San Diego-based battery-storage maker, hired Jing Nealis as CFO from EV-battery firm SES AI as it stands up domestic BESS manufacturing in Georgia (2 GWh initial capacity, targeting 8 GWh). She brings 20-plus years of energy-transition and manufacturing finance experience to the residential-to-utility/C&I expansion.

SEC filing

May 14

Steve Bond named Executive Vice President and President at NeoVolta Power LLC (from Chief Financial Officer, NeoVolta Inc.)

In the same announcement that named Jing Nealis CFO, NeoVolta's outgoing finance chief Steve Bond shifted to EVP and President of operating subsidiary NeoVolta Power LLC, taking direct charge of the company's Georgia battery-manufacturing buildout — a CFO-to-operations move that freed the finance seat.

SEC filing

May 14

Ravi Abbineni joined as Chief Financial Officer at ION Storage Systems (from Senior Vice President and CFO, JM Family Enterprises)

Maryland-based solid-state battery developer ION Storage Systems hired a finance chief from large privately-held JM Family Enterprises, signaling a push toward commercial scale-up of its solid-state cell technology.

Press release

May 14

Robert Vinje joined as Chief Operating Officer at Nextpower (from Chief Operating Officer, SOLARCYCLE)

Nextpower (the solar-tracker maker that rebranded from Nextracker in Nov 2025) hired SOLARCYCLE COO Robert Vinje as its COO — a SunPower and Amazon energy-operations veteran. Comp: $475K base, 70% target bonus from FY27, $4M FY27 equity award, $250K sign-on cash.

SEC filing

May 12

Marco Miller named Chief Project Development Officer at Nextpower (from Chief Operating Officer, Nextpower)

Nextpower's incumbent COO Miller shifts into a newly created Chief Project Development Officer role concurrent with Robert Vinje's COO appointment — reflecting the company's post-rebrand push into integrated power technology and project services.